On August 13, 2018, the Polk County Highway Department officially moved in to the new Highway Facility.  The facility opened to the general public on September 29, 2018.

View Site Photos

Take a tour via aerial footage and compare to the existing facility.

New Highway Facility

Detailed Information on Highway Facility Progress
In June of 2016, Former County Administrator Frey presented his annual condition of the County report to the County Board and citizens of Polk County.  "The condition of Polk County's infrastructure is good to excellent, with one huge exception," he said. The next few images displayed the aging and depleted infrastructures on the current Highway Facility campus.  He went on to explain how, for the first time in decades, Polk County can replace an obsolete, potentially dangerous and inefficient building with a reasonable structure that meets basic requirements without a tax increase.  The recommendations that followed Administrator Frey's presentation kicked off the Polk County Highway Facility project.

October Committee of the Whole - Project Update Committee of the Whole presentation on the Highway Facility Project - Update on budget and bid awards

September Committee of the Whole Presentation - Bid Awards and Next Steps Outline of the bid awards for work on the Bishop Building (Building 2) and outline of next steps for final bid issuance and awards.

Highway Facility 3D Rendering Final draft of preliminary design phase - Highway Facility 3D Rendering as of August 15, 2017

Preliminary Design Drawings - Highway Facility The preliminary design documents provide the outline for the high level decisions about the size, external materials, and placement of the new facility.

Frequently Asked Questions - Highway Facility Project Have questions about the project? This document compiles information relative to questions we've frequently received about the project. The document is updated regularly. If you have a specific project question, please contact Emil Norby at the Highway Department.

Presentation to the Committee of the Whole - March 2017 This presentation was given to the County Board in response to a resolution directing Administrator Frey to explore agreements with Bishop Fixtures and Millwork and the Village of Balsam Lake to obtain property and physical structures in the Balsam Lake Industrial Park.

Site Assessment Report - Parcel and Design Options Short Elliot Hendrickson, Inc. (SEH) completed a site assessment of industrial parcels in the Village of Balsam Lake in the Fall of 2016. These results were presented to the Executive Committee for consideration and recommendation to the County Board.

County Board acts to move forward with Bishop and Village Industrial Park properties The County Board votes to direct Administrator Frey to develop and negotiate preliminary agreements with the Village of Balsam Lake and Bishop Corporation towards the prospective purchase of lands located in the Industrial Park.

Polk County Highway Facility Changes

County_Garage_-_Image_2(1)_Web
Original Construction

Picture_-_Current_Building(1)_Web
Original Building - August 2018

Main_Building.rvt_2017-Feb-02_04-04-15PM-000_Perspective(1)_Web
New Building & Current Site