Northwest Region Construction Update from WisDOT

Northwest Region Construction Update

Ashland County
Highway:
WIS 13
Location: Jefferson Avenue in Mellen to Golf Course Road in the town of Morse.
Schedule: April 10 to November
Cost: $8.67 million
Description: Reconstructing WIS 13 from Jefferson Avenue to the north city limits; replacing the Bad River Bridge; grading to improve slopes and drainage; replacing storm and sanitary sewer, water main, sidewalk curb ramps, curb and gutter; and paving parking lanes, all in Mellen. Resurfacing WIS 13 from the north city limits to Golf Course Road in the town.
Traffic impacts: Northbound WIS is being maintained on either the north- or southbound lane of WIS 13 between Jefferson Avenue and the Bad River Bridge. Southbound WIS 13 traffic is being detoured via County GG and Thomas Street.

  • Truck traffic is being detoured via WIS 182, WIS 47, US 51 and US 2.

Buffalo County
Highway:
WIS 35
Location: Two are in Fountain City; one is northwest of Cedar Street, and the other is southwest of the intersection of WIS 35 and Old 35. The third is in the town of Buffalo northwest of the WIS 35/54 intersection.
Schedule: Feb. 28 to August
Cost: $4.25 million
Description: Replacing three bridges.
Traffic impacts: WIS 35 is open to one lane, with traffic controlled by temporary signals at all bridge locations and lanes having an 11-foot width restriction.

Chippewa County
Highway: County TT
Location: Cobban Bridge between Jim Falls and Cornell
Schedule: Aug. 8 to late October 2023
Cost: $4.7 million
Description: Replacing the bridge.
Traffic impacts: County TT in the work zone remains closed.

  • The shoulder and right-turn lane on northbound WIS 178 are closed by barrier wall.
  • The Old Abe Trail remains open.

Douglas County
Highway:
US 53
Location: County M to railroad tracks north of Solon Springs
Schedule: Aug. 8, 2022, to late May 2023
Cost: $6.88 million
Description: Repairing concrete along the entire length of the project; placing asphalt over the northbound lanes of the roadway from East Nyquist Road to the railroad tracks north of Solon Springs; milling and overlaying the shoulders and turn lanes along the entire length of the project; repairing or replacing culverts; replacing guardrail around the bridge over the railroad tracks north of Solon Springs; and replacing the concrete approach slabs on the south side of the north- and southbound US 53 bridges over the railroad tracks.
Traffic impacts: The driving lane on north- and southbound US 53 is closed. Other impacts are:

  • The US 53/North Boundary Road intersection in Solon Springs and the turn lanes from north- and southbound US 53 onto North Boundary Road will be closed to traffic at 6 a.m. Monday, May 1. That closure is expected to be in place for seven days.
  • The speed limit through the work zone has been reduced to 55 mph.

Dunn County
Highway: US 12
Location: Wilson Creek tributary north of I-94 in the town of Menomonie
Schedule: April 10 to late June
Cost: $1.29 million
Description: Replacing the culvert, removing guardrail and restoring the asphalt roadway and ditches.
Traffic impacts: US 12 is closed.

  • Through traffic is being detoured via I-94, WIS 128 and US 12.
  • Access is being maintained to commercial and private driveways in the work zone.

Eau Claire County
Highway:
I-94
Location: Just west of the WIS 312/County EE interchange to the Chippewa River Bridge northwest of WIS 37.
Schedule: July 11, 2022, to September 2023
Cost: $23.71 million
Description: Reconstructing east- and westbound I-94 by removing and replacing the existing pavement from WIS 312/County EE to County E, replacing culverts and guardrail, installing median cable barrier, restoring the ditches and slopes and placing new pavement markings. Making improvements at the I-94/WIS 312/County EE interchange, including replacing the joints on the bridge, overlaying the deck with concrete and replacing the pavement on either side of the bridge and the ramps. Resurfacing east- and westbound I-94 by milling and overlaying the existing asphalt pavement from County C to the Chippewa River Bridge.
Traffic impacts: Motorists will encounter bidirectional traffic on I-94 and WIS 312.

  • I-94 traffic is operating on the westbound lanes from County E to just west of the WIS 312/County EE interchange.
  • WIS 312 traffic is operating on the eastbound lanes in the interchange area.

Jackson County
Highway: WIS 121
Location: County FF South to WIS 95 west of Alma Center
Schedule: April 6 to June
Cost: $2.86 million
Description: Removing a portion of the existing pavement and placing new asphalt pavement; replacing culverts that have reached the ends of their service lives; upgrading guardrail; installing rumble strips; and replacing pavement markings.
Traffic impacts: WIS 121 is closed to through traffic for culvert replacement, with traffic detoured via WIS 95, I-94 and WIS 121.

Polk County
Highway: US 63
Location: St. Croix/Polk County line to County J south of the village of Clayton
Schedule: April 12 to late September
Cost: $5.71 million
Description: Replacing the pedestrian underpass east of 7th Street in the village of Clear Lake; milling off 2 inches of asphalt pavement and placing 3.25 inches of new asphalt; adding shoulder gravel to accommodate the highway profile increase; realigning the approach of County A/F at US 63 to achieve better sight distance at the intersection; realigning the approach of 60th Avenue at US 63; expanding the intersection tapers to meet current design standards; replacing guardrail; and cleaning, lining or repairing culverts and installing new end walls on some structures.
Traffic impacts: US 63 is reduced to a single lane of traffic at the pedestrian underpass east of 7th Street in Clear Creek.

  • Traffic is controlled by temporary signals, and 7th Street South is closed.
  • The 60th Avenue east and west intersections at US 63 are closed today through the end of next week.
  • Lane closures controlled by flagging are being used as necessary for culvert work.

St. Croix County
Highway: WIS 35
Location: County C in town of Somerset to Laser Drive in the village of Somerset
Schedule: April 26 to late October
Cost: $$6.57 million
Description: Replacing the pavement from County C to Laser Drive; upgrading the WIS 35/Church Hill Road/Main Street intersection and adding new traffic signals; and replacing and upgrading utilities.
Traffic impacts: WIS 35 is closed to through traffic from the WIS 35/Church Hill Road/Main Street intersection to Laser Drive, with traffic being detoured via Lagrandeur Road, Lemire Street, SMC Drive and Laser Drive.

Highway: WIS 65
Location: I-94 westbound ramp to just south of Wagner Drive in Roberts
Schedule: April 3 to November
Cost: $6.47 million
Description: Expanding WIS 65 from two to four lanes from the I-94 westbound ramp terminal to about 1,200 feet north of 70th Avenue; installing turn lanes, traffic islands and new traffic signals at the 70th Avenue intersection; upgrading drainage; placing permanent signage and new pavement markings; and modifying the park and ride lot.
Traffic impacts: Traffic on WIS 65 is limited to a single lane of traffic north of the roundabout north of I-94 for a short distance and is then split to one lane in each direction. In addition, the WIS 65/70th Avenue intersection has been shifted to the north, and traffic is controlled with temporary signals.

Highway: I-94
Location: Safety and weight enforcement facility (SWEF) off eastbound I-94 east of Hudson
Schedule: Sept. 12, 2022, to October 2023
Cost: $21.98 million
Description: Replacing the existing SWEF building with a modern one, reconstructing the parking lots and ramp/loop roadways and constructing an automated truck traffic monitoring system along eastbound I-94, a virtual weigh station along US 12 and an approximate 300-foot communications tower near the new building.
Traffic impacts: Motorists will encounter the following off-site impacts:

  • Westbound I-94:
    • There will be a continuous median shoulder closure with barrier wall until temporary widening of the eastbound median is removed later this summer.
  • Eastbound I-94:
    • There will be a continuous left-lane closure in the three-lane portion of I-94 near the US 12 interchange and lane shift until temporary widening of the eastbound median is removed later this summer.
    • There will be a continuous outside shoulder closure with barrier wall at the SWEF ramp locations until tie-in work is completed this summer.

Highway: I-94
Location: Rush River bridges west of Baldwin
Schedule: Sept. 7, 2021, to October 2023
Cost: $6.14 million
Description: Building temporary roadway and bridges to maintain four lanes of traffic on I-94; removing and replacing the existing east- and westbound I-94 bridges over the Rush River with structures wide enough to allow for an additional lane of traffic on I-94 when warranted, along with approach pavement; clearing and grubbing ditches; and installing storm sewer, signage, pavement marking, guardrail and fence.
Traffic impacts: Motorists will encounter the following closures for the coming week:

  • Eastbound I-94 lane closures:
    • 7 p.m. Sunday to 10 a.m. Monday.
    • 5 p.m. Monday to 2 p.m. Tuesday.
    • 5 p.m. Tuesday to 2 p.m. Wednesday.
    • 5 p.m. Wednesday to 11 a.m. Thursday.
    • 6 p.m. Thursday to 9 a.m. Friday.

Highway: I-94
Location: Carr Creek south of Woodville and County NN between County B and WIS 128
Schedule: July 19, 2021, to November 2023
Cost: $21.6 million
Description: Building temporary roadway and bridges to maintain four lanes of traffic on I-94; removing and replacing the existing east- and westbound I-94 bridges over Carr Creek and County NN with structures wide enough to allow for an additional lane of traffic on I-94 when warranted; constructing eastbound exit ramp and westbound entrance ramp bridges and realigning the ramps at the I-94-County B interchange; extending the north end of the existing box culvert at County NN; and completing grading operations, approach work, sign installation and pavement marking.
Traffic impacts: Motorists can expect to encounter the following lane closures on I-94 for the coming week on:

  • Westbound I-94:
    • 8 p.m. Sunday to 2 p.m. Monday
    • 5 p.m. Monday to 2 p.m. Tuesday
    • 5 p.m. Tuesday to 2 p.m. Wednesday
    • 5 p.m. Wednesday to 2 p.m. Thursday
    • 6 p.m. Thursday to 11 a.m. Friday
    • 7 p.m. Friday to 10 a.m. Saturday
  • Eastbound I-94
    • 6 p.m. Sunday to 10 a.m. Monday
    • 5 p.m. Monday to 2 p.m. Tuesday
    • 5 p.m. Tuesday to 2 p.m. Wednesday
    • 5 p.m. Wednesday to 10 a.m. Thursday
    • 6 p.m. Thursday to 9 a.m. Friday
    • 8 p.m. Friday to 9 a.m. Saturday

In addition:

  • Traffic at Carr Creek is expected to be switched onto the eastbound crossover Sunday night.
  • County NN will be closed from Wednesday to Friday, May 3 to 5.
  • Motorists will encounter flagging on the eastbound I-94 off-ramp at County B.

Trempealeau County
Highway: I-94
Location: County NN north of Osseo to the east county line
Schedule: July 18, 2022, to November 2024
Cost: $23.69 million
Description: Removing and replacing existing east- and westbound I-94 and I-94/US 10 interchange ramp concrete pavement, adding right-turn lanes at the I-94/US 10 interchange in Osseo and completing a polymer/chip seal on the US 10 bridge over I-94.
Traffic impacts: I-94 is open to two lanes of traffic in each direction, but motorists might encounter single-lane closures during off-peak travel times.

  • Eastbound I-94 traffic is operating on temporary lanes built in 2022.
  • Eastbound ramp traffic at the I-94/US 10 interchange are using temporary ramps until the permanent ramps are completed in late August.

Washburn County
Highway: WIS 77
Location: County I west of the village of Minong east to County M
Schedule: April 10 to late July
Cost: $8.48 million
Description: Removing a portion of the existing pavement and placing new asphalt pavement; cleaning, repairing or installing new culverts; reconstructing sidewalk curb ramps in the village of Minong; replacing deteriorated curb and gutter in the village of Minong; replacing guardrail; placing centerline rumble strips in rural areas; and installing new pavement markings.
Traffic impacts: Motorists on westbound WIS 77 will encounter a shoulder closure in the village of Minong for curb and gutter work.

Highway: US 53
Location: Pine Grove Road southeast of Shell Lake to Wildcat Road southeast of Spooner
Schedule: Aug. 15, 2022, to October 2023
Cost: $16.8 million
Description: Removing the existing pavement and a portion of the existing base course; placing a new base aggregate layer for drainage and new concrete pavement; replacing storm sewer, culverts, curb and gutter; reconstructing the approaches to US 53 from existing intersections; replacing shoulder rumble strips; and placing pavement markings.
Traffic impacts: One lane of traffic in each direction is being maintained on the southbound lanes.